Synagogue Expansion Project
Synagogue Expansion Project
Updates and Naming Opportunities
Construction Update 3/4/15
Dear friends and members,
We are pleased to share with you the following updates regarding our synagogue expansion project:
- The roof has been completed and passed inspection;
- Both men and women's mikveot are 80-90% complete and already look stunning;
- Installation of all the windows and doors for the social hall (ballroom) were installed today;
- We are waiting for the last door to the full service commercial kitchen to be installed to be completely weatherproof;
- Exterior stucco is complete.
Currently, we have begun our next fundraising round for the interior build-out and really count on your continued help in obtaining this goal. This next phase includes construction of the Learning center, Beit Din and business offices, the daily prayer sanctuary, and site work.
We have a number of naming opportunities available. Please contact our office at 954-983-9981 to learn more or to schedule an appointment for a legacy donation.
Sincerely,
Board of Directors and the Construction Committee
Thu, May 29 2025
2 Sivan 5785
Privacy Settings | Privacy Policy | Member Terms
©2025 All rights reserved. Find out more about ShulCloud